You don't have javascript enabled. Good luck with that.
Pencarian
Progres Pembangunan JIS Capai 34,13 Persen
.
photo Wuri Setyaningsih - Beritajakarta.id

Process of JIS Construction Reaches 34.13 Percent

PT. Jakarta Propertindo (Jakpro) continues the construction work of Jakarta International Stadium (JIS), in Tanjung Priok, North Jakarta. Entering the 61st week, its progress has reached 34.13 percent.

We are currently installing hybrid grass in training field 1

Corporate Communication and Commercial for JIS Project, Arnold Kindangen mentioned, his side deployed 1,700 workers for JIS construction project.

"We are currently installing hybrid grass in training field 1. Previously, we have completed grass installation in training field 2," he added, Thursday (11/5).

Jakpro is Committed to Finish JIS Project on Time

Grass installation is targeted to finish in December 2020. Next, his side still needs to finish constructing 8 main columns using slipform and start the pierhead work, precast installation on southern side of the stage.

"This project is estimated to employ 5,000 workers in 2021. We hope they can contribute to recover the economic since this project involves many vendors related to construction and material supply," he said.

Linked News
Popular News indeks
  1. Transjakarta Officially Opens School for Bus Drivers

    access_time20-11-2024 remove_red_eye1037 personAldi Geri Lumban Tobing
  2. Acting Governor Teguh: Coastal Seawall Construction Begins in 2025

    access_time20-11-2024 remove_red_eye903 personFolmer
  3. Legislator Ahmad Lukman Jupiter Wants PT FSTJ Add Shop Cars

    access_time19-11-2024 remove_red_eye545 personDessy Suciati
  4. PMPTSP Agency Launches PIN Greenvest to Prompt Green and Sustainable Investment

    access_time21-11-2024 remove_red_eye447 personAldi Geri Lumban Tobing
  5. Transjakarta Extends its Operation to 11 PM Today

    access_time19-11-2024 remove_red_eye379 personAldi Geri Lumban Tobing